DBKK High Risk on Komplex Karamunsing


Wednesday, 26 January 2011 admin-s
E-mail Print PDF
Digg!Del.icio.us!Google!Live!Facebook!Technorati!StumbleUpon!MySpace!Yahoo! Twitter!LinkedIn! 

"There were deflection as much as 3" or more on all the 3 floors. Certain crucial reinforcement were apparently not in the correct position resulting in very short lever-arm and hence structurally inadequate. With age and the effect of creeps, the deflection can only get worst. The 3 floors were reported to be in a "plastic" stage, and it was declared unsafe."

The owner (Suria Group) of 7, 8 and 9th Floor (staffs) heard cracking sounds inside the building and got worried. Suria then engaged a reg. Professional Engineer Ir. Tsen to carry out an investigation and found (declared) the 3 floors unsafe. This Eng. presented his report to a specially called High Risk Committee by DBKK and below are the confidential minutes. 

Yesterday, Joint professional Bodies (IEM, ACEM, SEA and PAM with the support of SLA 'Sabah Law Asso.' called a meeting and have writen a joint letter (signed by 3 professional bodies) addressed to the Mayor of DBKK to express their concern on this report. They are asking the Mayor to inform all other unit owners of Komplex Karamunsing Block C and to carry out a necessary structural check for the whole 3 Blocks which was and is still under massive Extensions and Renovations which caused many public concerns not only to its structural integrity but FIRE safety which even the Bomba Sabah director has expressed concern during his few professional dialogues with professional bodies at Bomba HQ KK. His comments were even quoted in www.pamsabah.com web site.

pg1

pg2

pg3

pg4

 


Comments (17)Add Comment
...
written by Bosousada, January 28, 2011 15:49:28
People become scare to visit Karamunsing after hearing this news.. That's why some party only keep quiet.. Takut rugi... Investment mahal. But remember people, a life is irreplaceable.
...
written by Devoe, January 28, 2011 10:45:56
I hope that Centre Point or Wisma Merdeka won't be the next.
...
written by sioponthan, January 28, 2011 08:29:45
no need to repair it. just construct a new building.
...
written by NollanBD, January 27, 2011 21:24:47
The big question here is: Who approved the ongoing massive renovation and extension? Why was it approved? Datuk Mayor, the rumors going around about the few lots given to you explains the ongoing renovations without prior approval from DBKK? Is it true?
...
written by Surand85, January 27, 2011 16:19:18
give attention with this problem..
...
written by lysa, January 27, 2011 15:10:21
Serious matter, indeed! really hope something can be done before its collapse. I just realize that the building was the 1st in KK. The 1st shopping mall in kk, Karamunsing.
...
written by Devoe, January 27, 2011 14:37:33
OMG! I hope I won't be singing ' Karamunsing is going down, is going down '. smilies/cheesy.gif
...
written by Andykhai, January 27, 2011 13:50:05
This requires serious attention and immediate action..
...
written by LimD, January 27, 2011 13:48:48
This is a serious matter and should be taken action immediately. It's best for the people to evacuate from that building for their safety sake.
...
written by popuri, January 27, 2011 13:47:48
I'll stay away from there from now on.
...
written by bulletpain, January 27, 2011 13:47:20
please repair before late.
...
written by Old Man, January 27, 2011 09:36:33
Here in Sabah, there's a on-going "practice" that a handful of Consulting Engineers have certain "understanding" with some Contractors!
One Ir WD Lee even demanded a Contractor friend of mine to use HUME products! NEVER stated Or Equivalent!
Some claimed that their Fees charged against the Developers were too low. As low as 2% and therefore they have to 'negotiate' with the Contractors... Result: Specifications were compromise!
Sometimes, they even demand for donations as if the Contractors owe them a living!
Otherwise they would not recommend the Letter of Award to the potential Contractor for a Project.... Disgusting! Know How is not important. Know Who becomes the order of the day!
Another issue is that some Project Consultants have passed the age of 65 and yet are not giving way to the younger generation. Want to bring more money into their graves or what???
...
written by SoundMan, January 27, 2011 09:13:26
smilies/grin.gif What is the City Mayor waiting for ?

The owner of the Complex is a particular friend of the Chief minister Musa Aman, and you would not want your mentor's to upset his friend .....would you ? Or would you!smilies/angry.gif
...
written by Susuit, January 27, 2011 07:55:35
Do something fast before it's too late !!!!
...
written by carlitos, January 26, 2011 21:53:04
Its funny there is no mention about it in any local papers in Sabah?? and how come the Mayor of Kota Kinabalu keeping quiet about it?

He must be taking something under the table as he let this happened when he is still in charge. If anyone died, it is the "politically appointed" Mayor of Kota Kinabalu Iliyas and also the CM who have blood in their hands.

The Mayor of Kota Kinabalu obviously not looking after the public interest.
...
written by carlitos, January 26, 2011 21:46:15
Imagine how many people will die if the building collapse during the weekends or public holiday and its full of people..
...
written by Ezzy, January 26, 2011 17:43:09
aiyooo.. Mayor, you need to evacuate them fast ! BTW why did you allow the non-stop renovation and extension to the original structure? That building is getting fatter and fatter, heavier and heavier each day. Remember Sampoong Department store in Korea? Please listen to the experts before it is too late.

Write comment
This content has been locked. You can no longer post any comments.

busy
 

Language Translation

TwitterFacebook Twitter

ARCHIVES 2011

DPM rubbishes Bangladeshi votes-for-citizenship claim

By Yow Hong Chieh, The Malaysia Insider KUALA LUMPUR, Sept 18 — Tan Sri Muhyiddin Yassin has denied claims that the Barisan Nasional (BN) government has given Bangladeshi workers ...

Something is rotten about migrant workers’ entry rules

By John Inbaraj, Aliran Something is seriously wrong with the entire undocumented immigrants issue. There seems to be a complete lack of will on the part of the ...

Stop infighting or risk losing, BN leaders told

By V. Shankar Ganesh, Minderjeet Kaur and G. Surach, NST SHAH ALAM: Barisan Nasional leaders in Selangor have been urged to sign a pledge that they will not be involved ...

Khalid has constitutional right to choose state secretary, says ex-jurist

(The Malaysian Insider) - The ongoing row over Datuk Mohd Khusrin Munawi’s appointment as Selangor’s No. 1 civil servant deepened as another retired judge waded into the fray ...

Tuanku Titah Perbincangan Selangor-SPA Untuk Penyelesaian Terbaik

Saya telah mengadap DYMM Sultan Selangor hari ini bagi membincangkan isu pelantikan Setiausaha Kerajaan Negeri....

Hundreds stage protest against developer

By The Star KUALA LUMPUR: Hundreds of people, including residents, non-governmental groups and politicians, staged a protest at the Bandar Tasik Selatan LRT in Cheras against the Bandar ...

The Religious Pluralism Debate: A Critique.

By Dr.Dzul As the curtain draws to a close for the last year of the first decade in the third millennium, I wanted to just sit back and peruse the ...

PM to meet BN MPs over snap polls

By Asrul Hadi Abdullah Sani, The Malaysian Insider KUALA LUMPUR, Jan 1 — Datuk Seri Najib Razak is scheduled to meet with all Barisan Nasional (BN) lawmakers next Saturday ...

No more free plastic bags in Penang

By Debra Chong, The Malaysian InsiderShoppers in Penang will be charged 20 sen for each plastic bag everyday from today, as the state government steps up its green campaign....

Power to build nation is with the people, says Najib

By The Star KUALA LUMPUR: Malaysians must fulfil their responsibility in building a better future for the coming generations and place the country in its rightful position, said ...

You are here: Home ARCHIVES ARCHIVES 2011 DBKK High Risk on Komplex Karamunsing

Latest Posts - Archives 2011

Popular Posts - Archives 2011